| 2013 | Packet Sorter, Commissioning - upgrade of PLC system from S5->S7 |
Nike, Belgium | ![]() |
| 2013 | Semi Portal Reclaimer, Commissioning Automated gypsum storage – part of the flue gas desulfurization (SO₂) treatment system |
ČEZ ELE, Ledvice, Czech Republic |
|
| 2013 | Assembly Line, Montage, Commissioning production facility of parts for gearboxes |
ZF Holýšov, Czech Republic |
![]() |
| 2013 | Mail Center – Packet Sorter, Commissioning Upgrade of sorting capacity at more places in Germany. General contractor: BEUMER. |
DHL, Germany | ![]() |
| 2014 | Phosphate ball mill, Commissioning, Contractor: ThyssenKrupp SIMATIC S7-400 H, 6 kV D/Y salt water starter, MCC, chemical facility Link |
JIFCO, Eshidiya, Jordan |
![]() |
| 2015 | Stacker, modification Increase of limestone stacking capacity from 1,000 t/h to 2,000 t/h Installation of new motor and gearbox, belt drum and soft starter Solving issues with supply power lines Contractor: SCHADE Lagertechnik GmbH Link |
Sichuan Yadong Cement Corporation, Cheng-du, China |
|
| 2015 | Semi Portal Reclaimer ×2, Stacker ×2 – electrical site manager, commissioning Automated coal strorage at new Steel factory. Rockwell PLC, 6kV cable drum with fiber optic included, 6kV dry transformer onboard, frequency converter inside delta connection Contractor: SCHADE Lagertechnik GmbH |
Formosa, Ha Tinh Vietnam |
|
| 2015 | Fleece production line – electrical site manager, connection after transport, commissioning Contractor: TRIMA |
Owens Corning, USA |
![]() |
| 2015 2016 |
Semi Portal Reclaimer ×4 – PLC programmer, commissioning Contractor: SCHADE Lagertechnik GmbH Link |
STX, South Korea |
![]() |
| 2016 | Portal Reclaimer, Commissioning| Kazchrom, Kazakhstan |
|
![]() |
| 2017 | Bridge Reclaimer, Commissioning Contractor: SCHADE Lagertechnik GmbH |
Société des Ciments de Beni Saf - Algeria |
![]() |
| 2017 | Stacker / Reclaimer, Inspection of the old machines in very agressive enviroment | Dead See Works, Israel |
![]() |
| 2017 | Commissioning of two large machines for stretching rolled aluminum sheets. The machines were equipped with an underground oil pumping station and a hydraulic cylinders with a forces of up to 120 MN. PLC SIEMENS S7 with safety integrated, large PRIFINET network. Contractor: SMS Meer |
KUMZ Kamnesk Uralskij, Russia |
![]() |
| 2017 2019 2020 2021 |
Assembly Line, Montage, Commissioning |
Interkov Benešov nad Ploučnicí, Czech Republic |
![]() |
| 2018 | Semi Portal Reclaimer / Combi Stacker, Software & HMI, SCADA, TAKRAF | Bao-Steel Shanghai, China |
![]() |
| 2018 | Bridge Portal Reclaimer / Stacker, Software & HMI, SCHADE | Bao-Steel Shanghai, China |
![]() |
| 2018 | Commissioning of two Semi Portal Reclaimers, first machines programmed in SIEMENS TIA PORTAL Contractor: SCHADE Lagertechnik GmbH Link |
Dragon Steel, Taichung, Taiwan |
![]() |
| 2018 2019 |
Semi Portal Reclaimer, Commissioning |
PhosAgro Cherepovec, Russia |
![]()
![]()
![]() |
| 2019 2021 |
Ship Loader – Bulk Material, Commissioning and modifications | Port Kotka, Finland |
|
| 2019 | Hardening Furnace, Modifications |
Benteler Holland, MI, USA |
![]() |
| 2020 | Triple Wagon Unloader, Commissioning . |
OTEKO Taman, Russia |
![]() |
| 2020 2021 |
Ball Joint Assembly Line, Modifications & Translations ............................. | Mubea Žebrák, Czech Republic -> Kežmarok, Slovakia |
![]() ![]() |
| 2020 2021 |
EOL Tester, Maintenance & Modifications | Black & Decker, Czech Republic |
![]() |
| 2021 | Commissioning of next two Semi Portal Reclaimers, Contractor: SCHADE Lagertechnik GmbH Link | Dragon Steel, Taichung, Taiwan |
![]() |
| 2021 2022 |
In-Pit Crushers & Conveyors – S/R, Commissioning ..................................... | LGOK, Russia |
![]() |
| 2022 | Container Handling Automation, Commissioning of automated crane area | DP World Antwerpen, Belgium |
![]() |
| 2023 | Robotic Cell, Commissioning of VAX station for front axle crosmember |
Benteler Rumburk, Czech Republic |
![]() |
| 2023 2024 |
Robomould® Projects – Montage & Commissioning ......................................... | AMS Belgium – BE / FI / DE / FR | ![]() |
| 2023 | MQB Battery Assembly Line – Improvements, PLC ........................................ | Škoda Auto, Czech Republic | ![]() |
| 2024 | Robomould® Finishing Projects – Montage, Commissioning, Remote Support .............. | AMS Belgium – BE / FR / FI / DE | ![]() |
| 2024 | Robotic Hotmelt Glue Line – New Project Integration .................................. | DRÄXLMAIER, Germany / Poland | ![]() |
| 2024 | Robotic Grinding & Welding – PLC Commissioning & Improvements ...................... | SP-tech / EFAFLEX, Czech Republic | ![]() |
| 2024 | Robotic Grinding Line for Windshield Glass – Commissioning & HMI Translation ...... | SGS, Czech Republic | ![]() |
| 2025 | Electronic Module Assembly Line – PLC Support & Improvements (TIA18) .............. | Vitesco Technologies, Czech Republic | ![]() |
| 2025 | Roof Upholstery Assembly Line – Adding New References (Step7, WinCC 2008) ......... | GA Ostrava, Czech Republic | ![]() |